The 2027 Budget Is the Last One That Can Still Move Your ECC Date
Budget season is quieter than go-live season. It is also where most ECC timelines are genuinely decided.
Run the arithmetic on what is happening in boardrooms right now. A budget approved in September or October 2026 funds work that starts in January 2027. Mainstream support for ECC ends on December 31, 2027. That leaves twelve months. Strip out the final quarter, because the last quarter of any SAP programme is cutover, hypercare and stabilisation rather than build, and you are funding roughly nine months of usable delivery. There is no second attempt inside that window.
Most organisations get the money right. Licences are modelled carefully. The system integrator contract is negotiated hard. Infrastructure and cloud consumption are forecast to the quarter. Then the internal and contract capacity that actually carries the work gets written as a single line: a headcount total, or a percentage of the SI contract value.
That line is where the date is set, and almost nobody treats it that way.
A number is not a schedule
A staffing budget expressed as a total assumes availability. It assumes that when the plan calls for a data migration lead in February 2027, a data migration lead can be found in February 2027. For most of the last decade that assumption held well enough. In 2027 it stops holding, for a straightforward reason: every organisation still on ECC is working to the same date, drawing from the same pool, in the same months.
The pattern we keep running into is not that programmes are underfunded. It is that they are funded without a sequence. The money is approved. The roles are not named. The start months are not written down. Nobody owns securing the scarce skills, so it happens when someone has time, which is usually after the programme has already started.
What this looks like when it goes wrong
It rarely looks like a crisis in month one. The core team lands roughly on time, because the core team is the easiest part of the plan to fill. Functional leads are identified early, often internally, and the programme feels properly staffed at kickoff.
The gap surfaces in month five or six, when data migration and authorisations are supposed to be running in parallel with build and one of them started late. By then the buffer has already been spent absorbing the delay quietly. The steering committee sees a schedule that is still green, right up until the first mock cutover runs long and there is no recovery room left in the calendar.
At that point the options are all expensive. Rates in the second half of 2027 will not resemble rates today. Scope reduction late in a programme costs more than it saves. And extending past December 2027 means paying for extended support while still carrying the programme.
The more useful budget question
The standard question in a budget review is what the programme costs. The more useful question is what the programme costs if the people it depends on are not available in the month the plan assumes they start.
Three things worth checking before anything gets signed this autumn.
Does the staffing line name roles and months, or only a total? A total headcount cannot be tested. A list of roles with start dates can be, and the test is simple: for each role, how long does it currently take to secure someone credible, and does that lead time fit before the start date?
Is there contingency for rate movement in late 2027? Not a generic percentage. A view on which specific roles are most exposed and what happens to the plan if they cost meaningfully more in nine months than they do now.
Who owns securing the scarce roles, and when do they start? If the answer is the programme manager, the answer is effectively nobody, because the programme manager will be fully loaded from day one.
The takeaway
The date does not slip at go-live. It slips in a budget review, in a meeting that felt like a finance conversation, when a staffing plan was approved as a number rather than as a schedule.
There is still time to fix that this autumn. There will not be next autumn.